Meeting Overview


Completed Action Items from Last S2P Sprint 4 PM Bi-Weekly (March 12, 2025):

Action Item Owner(s) Status
Follow up with leads to finalize MVP development plan Egonna Aboh ✅ Completed
Distribute Kanban board link and ensure task visibility Lisa ✅ Completed
Finalize Sprint KPIs and client status report Gelon Brumfield ✅ Completed
Distribute and analyze team survey Spencer Fong ✅ Completed
Coordinate with research & strategy to clarify KPIs Lisa ✅ Completed
Continue impediment tracking and updates in Notion PM Team ✅ Completed
Prepare phase 1 project charter draft PM Team ✅ Completed

Key Discussion Points

  1. Feedback on Demo Narratives & User Engagement Metrics:
  2. MVP Development Plan Progress:
  3. Usability Testing & Data Analysis:
  4. Sprint 4 Demo Preparations:
  5. Case Study Template Discussion:
  6. Project Communication & Contact List Updates:

Action Items

Action Item Owner(s) Due Date
Provide structured email context for external consultants/interviews Gelon Brumfield ASAP
Review contact list, remove Rana & Jin Young, check on Jeffrey’s status Spencer Fong ASAP
Review metrics & data used in PDF report Lisa Before Sprint 4 Demo
Prepare sprint roadmap slide with cycle time metrics for demo presentation Gelon Brumfield Before Sprint 4 Demo
Sync case study progress with product strategy team during sprint planning Spencer Fong, Gelon Next Sprint Planning
Align demo presentation with client feedback, ensuring narrative consistency PM Team & Leads Before Sprint 4 Demo

Next Steps