Meeting Overview
- Date: January 31, 2025
- Attendees: PM Team
- Purpose: PM Sync
Goals
- Project Updates and Scope Re-Alignment
- Meeting Scheduling and Preparation
- Team Coordination Updates
- Team Charter Finalization
- Stakeholders Report Overview
Action Items
PM Action Items
Notes
Key Discussion Points
1. Project Tracking & Sprint Planning Updates
- Gelon Brumfield emphasized the importance of aligning project tracking and sprint planning.
- Updates were provided on backlog management:
- Sprint 1 tasks need to be documented in the Gantt chart.
- Spencer Fong and Gelon will work together to input all sprint-related tasks.
- Clarification on task management:
- Kanban Board – Houses all project tasks.
- Agile Backlog – Will only include user stories moving forward.
- Gantt Chart – Used for timeline tracking, stakeholder reporting, and dependency management.
2. Sprint 1 Stakeholder Report & Project Documentation